Construction Update as of February 21
The ground level was very low. In some places, we had to dig down to 1.8 meters. To ensure the foundations were strong enough, we decided not to compensate by raising the…
The ground level was very low. In some places, we had to dig down to 1.8 meters. To ensure the foundations were strong enough, we decided not to compensate by raising the…
The first tie beam is poured over the concrete foundations. https://youtu.be/Egpul_5bSt8
Construction of the sunken living room. https://youtu.be/Zi_axKJqCk4 And once the concrete has been poured... https://youtu.be/DyYVR3ziuU8
Machinery that allows for faster production with less effort. Note that the cart collects a gravel-sand mixture. It is mixed in a 60/40 ratio to produce what is known as concrete…
We're pouring concrete footings. https://youtu.be/3XZjw2WqClI
We are working on the retaining walls and footings. https://youtu.be/HVA9HLDu5Xs
We’re continuing work on the foundation. The excavation at this site will be deeper, as the solid soil is much lower than it was for the first house. Much more…
We are continuing with the grouting work, preparing the excavation sites, and preparing the steel for the footings. https://youtube.com/shorts/TW-8QftT22g
Just like with the first house, we dig down to solid ground and backfill with cyclopean concrete. https://youtube.com/shorts/s-esVkuEm0A
We're starting work on the foundation for the second house. https://youtube.com/shorts/Z0z3MMTWayE